Berlin Plans 14-Month Ringbahn Closure Starting in June 2030

Berlin's eastern Ringbahn would lose S-Bahn service between Frankfurter Allee and Ostkreuz for 14 months beginning June 28, 2030, under plans to replace three railway bridges. The project remains subject to approval and is among several major rail clos...

lake-av1wquo49a1aoxfadqulihev-b8769116-ff73-4d01-8365-34cfaab6807e-0.webp

AI summary

  • Four S-Bahn lines, the S41, S42, S8 and S85, use the section, with roughly 630 trains passing through each day.
  • Replacement buses would connect Frankfurter Allee and Ostkreuz via Gürtelstraße, which should stay largely open to road traffic.
  • Two steel arch bridges with clear spans of 63 and 65.85 meters are proposed, about 20 meters longer than the existing structure.
  • The selected option has the shortest overall schedule at 20 months and requires cutting down 120 trees.
  • Public objections can be submitted from October 20, 2026, through December 21, 2026, under the formal plan approval process.

Four S-Bahn lines affected

The planned closure covers a section used by the S41, S42, S8 and S85, with roughly 630 trains passing through each day, according to DB planning documents reported by Berliner Kurier and nd-aktuell on November 16–17, 2026. Tagesspiegel and Berliner Zeitung have also reported on the planned disruption.

Replacement buses would connect Frankfurter Allee and Ostkreuz via Gürtelstraße, which is expected to remain largely open to road traffic during construction.

To allow S-Bahn services to continue outside the closed section, the plans call for a double crossover north of Frankfurter Allee station and a temporary facility where trains can reverse north of Ostkreuz. Even with those arrangements, not all trains are expected to reach the two stations.

Three aging bridges to be replaced

DB plans to replace the railway bridges over Gürtelstraße in Friedrichshain and over Wartenbergstraße and Tasdorfer Straße in Lichtenberg. The Gürtelstraße bridge, built in 1910, has substantial damage, making its replacement particularly urgent. The two Lichtenberg bridges have also reached the end of their intended service lives; DB InfraGO documents cited by Entwicklungsstadt and nd-aktuell date both to 1927.

At Gürtelstraße, DB proposes two steel arch bridges with clear spans of 63 meters for the S-Bahn and 65.85 meters for the long-distance tracks. The replacement crossing would be about 20 meters longer than the existing structure, which measures roughly 47 meters. Planning documents put the estimated cost of this crossing alone at about 73.5 million euros, excluding the two Lichtenberg bridges.

The closure would also affect tracks used to move ICE trains to the Rummelsburg depot. Although no regular long-distance passenger service currently runs there, nd-aktuell reports that the tracks normally carry operational movements of long-distance trains and a few freight trains each day. They provide the shortest connection between the tunnel section of Berlin Hauptbahnhof and the ICE depot.

The Ringbahn tracks also serve as a diversion route for regional trains during other closures. As of November 2026, RE2 trains are using the route because of the Stadtbahn closure.

Construction schedule, trees and noise barriers

DB selected the construction option with the shortest overall schedule: 20 months, according to planning documents reported by nd-aktuell. Its 14-month full closure of both pairs of Ringbahn tracks would be only half a month longer than under alternatives that temporarily moved S-Bahn trains onto the long-distance railway alignment. Those alternatives would require a significantly longer overall construction period and additional single-track closures.

The selected option would require cutting down 120 trees, more than any other option examined. Even the alternative that preserved the most trees would require removing 80, according to nd-aktuell and Berliner Kurier.

New noise barriers are also planned. Along the east side of the tracks, a continuous wall would extend for 454 meters at a height of six meters. On the west side, barriers ranging from three to six meters high would cover 513 meters, nd-aktuell reported.

Other major closures planned

Elsewhere in Berlin, plans call for an eight-week shutdown of train services between Hauptbahnhof and Spandau on the Stadtbahn. Felix Berschin, a board member of the MehrBahn think tank who reviewed DB InfraGO's plans for 2029 and 2030, told Berliner Zeitung that this closure would cancel 40 percent of long-distance trains and 70 percent of regional trains.

Berschin said passengers and train operators should expect severe restrictions, with almost all Berlin routes affected. The connection between Gesundbrunnen and the lower-level station at Hauptbahnhof would also close for 56 days.

South of Berlin, construction on the Anhalter Bahn would require a 57-day full closure. During that period, train service between Berlin Hauptbahnhof and BER airport would fall by about a quarter, while only every second train would run between Wannsee and Bad Belzig.

A separate Anhalter Bahn closure is planned for fall 2030. It would halt trains between Ludwigsfelde and Bitterfeld for 56 days.

Public objections open through December

The Ringbahn bridge project is still undergoing the formal plan approval process, known as the Planfeststellungsverfahren, overseen by the Eisenbahn-Bundesamt. DB InfraGO filed its application on May 13, 2025, according to Entwicklungsstadt and Berliner Kurier.

The period for submitting public objections and statements opened on October 20, 2026, and runs through December 21, 2026. The project is listed on the federal participation portal under reference V-E100501.

#Berlin#Deutsche Bahn